# Sprint Meeting Notes
*note: replace anything surrounded by << >> and **remove** the << >>*
**Attended**: Spencer Powell
**Attended**: << record the team members in attendance (virtual counts as long as they are participating) >>
**DATE**: << meeting date >>
**DATE**: 3/17/2025
***
## Sprint << num >> Review
## Sprint 2 Review
### SRS Sections Updated
<< List any SRS sections that were updated in the last sprint >>
None
### User Story
<< Corresponding User Stories completed in this sprint >>
None
### Sprint Requirements Attempted
<< The corresponding SRS requirement that the team completed in the last sprint >>
None
### Completed Requirements
<< The work that's been completed in this sprint >>
None
### Incomplete Requirements
<< The work that has not been completed in this sprint. Be VERY detailed and specific regarding what isn't working and what needs to be completed >>
- Timing information for OCCT is a work in progress
- work on the client hasn't started
- api endpoint that makes a route isn't mocked or working
- while the data for the trips/stops is gathered the setup for the server to provide that data to the client isn't made yet
### The summary of the entire project
<< A general overview of the entire project >>
Still very much in an early messy state.
***
## Sprint << num >> Planning
## Sprint 3 Planning
## Requirements Flex
<< # >>/5 requirement flexes remaining
4/5 requirement flexes remaining
## Technical Debt
<< Any requirements from the previous sprint that are using a technical flex >>
Connecting up the client and the server/putting data in desired format
### Requirement Target
<< The corresponding SRS requirement that our team will be complete in next sprint >>
- Convert data into desired format from data available via APIs
- Client and server should integrate without issue
### User Stories
<< Corresponding User Stories >>
Initial user story
### Planning
<< Our team's detailed plan to complete the sprint >>
Levi will finish up handling getting static timing for OCCT and build the client to display some data and Spencer will setup the server to show the generated files and for the api endpoint which gives a route have it emit a static hand-written route
### Action Items
@ -64,8 +66,8 @@
### Issues and Risks
<< A list of potential obstacles that could keep us from completing the sprint and what's being done about them >>
Other school work could take too much time and prevent progress from being made.
### Team Work Assignments
<< A list of each team member and their works assignments for this sprint >>
<< A list of each team member and their works assignments for this sprint >>